New Building: Theme Park LEGOLAND

A new theme park with rides, shows, stores, restaurants, and areas where kids are able to learn through play was built.

Projectdata

Client / Building Owner Kling Consult Ingenieurgesellschaft für Bauwesen mbH Krumbach / LEGOLAND PlanungsGmbH Günzburg
Time of performance / construction period 2000 - 2001 / Grand Opening 2002
Asset groups Sanitary Facilities, Heating, Ventilation, Electro-technics, Weak Current, and Drainage Technology
Phases of Construction LP4 - LP5
GFA 54 ha.
Project Details

A new theme park with rides, shows, stores, restaurants, and areas where kids are able to learn through play was built.

  1. Phase: designing construction documents including technical building services for the new "Administration Base Building" based on first drafts
  2. Phase: designing construction documents for sanitary facilities "Parkwide" based on first drafts
  3. Phase: designing construction documents for "Utilities network primary and secundary parkwide"
  4. Phase: designing construction documents for "Utilities under slab" for main and adjoining buildings
  5. Phase: designing coordinate plans for "Utilities network primary and secundary, water feature systems, power and communication network, cluster, parkwide, Miniland"


The major concern of this project was:

 

  • to design construction documents in German and in Englisch
  • to work WEB-oriented ("Active Project") in a team in order to exchange information worldwide